If an application for approval of a development agreement is not included as a part of a development permit application, a separate application for approval of a development agreement shall be submitted to the Director. Within ten (10) days following receipt of an application the Director shall determine if the application is complete. If it is not, it shall be returned by the Director to the applicant along with an explanation of the deficiencies in the application, and the applicant shall have ten (10) days within which to correct the deficiencies in the application and resubmit a completed application to the Director. If an application is determined to be complete, the Director shall proceed to schedule the application as set forth in section 9-9-10 of this chapter. (Ord. 3, Series 1999)