The town engineer shall assess the following fees and deposits:

A. Engineering Plan Review Fee: Each individual application for a building permit shall be accompanied by a nonrefundable engineering plan review fee. Fee amount shall be determined and adopted annually by town council through the annual budget adoption.

B. Right-of-Way Permit Fee: Each individual application for a right-of-way permit shall be accompanied by a nonrefundable permit and inspection fee. Fee amount shall be determined and adopted annually by town council through the annual budget adoption.

C. Right-of-Way Deposits: Prior to the issuance of a permit, a deposit in the form of a surety shall be assessed by the town engineer to cover the cost of restoring the right-of-way. The amount of the deposit shall be determined and adjusted by the town engineer and based on disturbance area and other conditions and circumstances of the project. If after issuance of a permit any deposit is determined to be less than sufficient to pay all costs, the contractor shall, upon demand, no later than ten (10) days after being billed by the town, or prior to the issuance of any further permits, pay to the town an amount equal to the deficiency. If the contractor fails or refuses to pay the deficiency, the town may institute an action to recover the amount in any court of competent jurisdiction and refuse to issue any subsequent permits. Until the deficiency is paid in full, no additional permits shall be issued. (Ord. 3, Series 2022)