A. Work authorized by the right-of-way permit shall be performed between the hours of seven o'clock (7:00) A.M. and seven o'clock (7:00) P.M., Monday through Friday (except holidays), unless the contractor obtains written consent from the town engineer to work earlier or later than the stated hours or on a weekend or holiday.

B. Street pavement cuts will not be allowed between November 1 and April 30, except when one (1) of the following conditions is met:

1. There is a public utility emergency with notification and approval by town engineer.

2. Special or unforeseen circumstances arise as determined by the town engineer.

If the town engineer approves a pavement cut between November 1 and April 30 due to one (1) of the conditions above, a special provision memo shall be prepared and submitted for review to the town engineer to accommodate pavement patching during winter conditions. Pavement repairs completed during this period shall be considered temporary and be removed and replaced as soon as conditions permit after April 30. The town engineer may require the applicant to post an additional deposit to cover additional costs associated with the winter condition street cut. (Ord. 3, Series 2022)